Friday, June 26, 2015

Moving Along

From Monday to Friday this week has been a transformation.  Material arrived on Monday... to now having walls (interior and exterior) with window/door openings and insulation siding.

This phase is occurring very fast.  Having to coordinate multiple contractors and material suppliers in a certain sequence has been a learning experience for me.  But is has been exciting too. 

 It's been like an ant hill of activity at times.  

Today the trusses arrived, the foam board insulation (blue siding) is going up, and the vertical posts are in place for the carport.  Monday, incidental trim-work will take place.  Tuesday, the trusses will go up.  Decking and dry-in will follow.  

Week three, windows and exterior doors will be installed.

                                            